High Plains Open Energy Data

Wyoming generation tracker

As of 16 November 2026. Statuses are as reported to EIA for 31 December 2025 in the EIA-860 2025 data release, the most recent final data. They will be updated when EIA publishes newer data.

Summary

For 2025, developers and utilities reported 17 active proposed generators in Wyoming, totalling 7,206.6 MW, against 12,735.6 MW of existing capacity. Of that, 3,550.5 MW was under construction.

A further 5 generators (621.1 MW) were reported as indefinitely postponed or cancelled, and are listed separately below. Two existing generators report a planned retirement.

Active proposed generators

PlantGeneratorTechnologyCapacity (MW)CountyOwner or operatorStatusPlanned operationEIA plant ID
Cowboy Solar IIC2BSBatteries200.0LaramieTGE Wyoming 225, LLCPDec 202769189
Cowboy Solar IIC2PVSolar Photovoltaic365.0LaramieTGE Wyoming 225, LLCTDec 202769189
Cowboy Solar ICLP20Solar Photovoltaic400.0LaramieCowboy Solar IPMar 202868022
Two Rivers Wind FacilityTR1Onshore Wind Turbine6.1CarbonTwo Rivers Wind LLCLOct 202863972
Cheyenne Prairie Generating Station02BNatural Gas Fired Combustion Turbine40.0LaramieBlack Hills Service Company LLCPDec 202857703
Cheyenne Prairie Generating Station03ANatural Gas Fired Combustion Turbine40.0LaramieBlack Hills Service Company LLCPDec 202857703
Cheyenne Prairie Generating Station03BNatural Gas Fired Combustion Turbine40.0LaramieBlack Hills Service Company LLCPDec 202857703
Cowboy Solar ICLPBSBatteries400.0LaramieCowboy Solar IPDec 202868022
Dutchman Solar generation and BESSDUTC1Solar Photovoltaic499.0ConverseDUTC bn, LLCLJun 202968317
Dutchman Solar generation and BESSDUTC2Batteries499.0ConverseDUTC bn, LLCLJun 202968317
Rail Tie WindCRTW1Onshore Wind Turbine504.0AlbanyRepsol Renewables NALJun 202964847
Goshen SolarGS1Solar Photovoltaic163.0GoshenGoshen Solar, LLCTDec 203067936
Kemmerer Unit 1KU1Nuclear500.0LincolnUS SFR Owner LLCLDec 203068635
Chokecherry and Sierra Madre WindI-AOnshore Wind Turbine844.2CarbonPower Company of Wyoming LLCUDec 203158987
Chokecherry and Sierra Madre WindI-BOnshore Wind Turbine849.6CarbonPower Company of Wyoming LLCUDec 203158987
Chokecherry and Sierra Madre WindII-AOnshore Wind Turbine1,303.2CarbonPower Company of Wyoming LLCUDec 203258987
Chokecherry and Sierra Madre WindII-BOnshore Wind Turbine553.5CarbonPower Company of Wyoming LLCUDec 203358987

Planned retirements

PlantGeneratorTechnologyCapacity (MW)OperatorPlanned retirementEIA plant ID
Dave Johnston3Conventional Steam Coal229.5PacifiCorpDec 20274158
Elk Basin Gasoline PlantGEN1Other Gases1.0Contango Oil and GasJan 202652127

How planned coal retirement dates have changed

EIA-860 records, each year, the retirement date that a plant's owner plans for each generator. Comparing the annual editions shows how those plans have moved. Between the 2023 and 2024 editions, 10 Wyoming coal units totalling 3,656.1 MW stopped reporting a planned retirement date: Dave Johnston 1, 2 and 4, Jim Bridger 1 to 4, Naughton 1 and 2, and Wyodak. Only Dave Johnston 3 kept its date, December 2027. Two of the units, Jim Bridger 1 and 2, had been converted to burn natural gas by the 2024 edition.

Unit2019202020212022202320242025
Dave Johnston 1nonenoneDec 2027Dec 2027Dec 2027nonenone
Dave Johnston 2nonenoneDec 2027Dec 2027Dec 2027nonenone
Dave Johnston 3Jan 2027Jan 2027Dec 2027Dec 2027Dec 2027Dec 2027Dec 2027
Dave Johnston 4nonenoneDec 2027Dec 2027Dec 2027nonenone
Jim Bridger 1nonenoneDec 2037Dec 2037Dec 2037nonenone
Jim Bridger 2nonenoneDec 2037Dec 2037Dec 2037nonenone
Jim Bridger 3nonenoneDec 2037Dec 2037Dec 2037nonenone
Jim Bridger 4nonenoneDec 2037Dec 2037Dec 2037nonenone
Naughton 1nonenoneDec 2025Dec 2025Dec 2025nonenone
Naughton 2nonenoneDec 2025Dec 2025Dec 2025nonenone
Naughton 3nonenoneDec 2029Dec 2029Dec 2029nonenone
Wyodak 1nonenoneDec 2039Dec 2039Dec 2039nonenone

"None" means that edition reported no planned retirement date for the unit. The table shows the editions from 2019; earlier editions, back to 2001, are in the full history. The only earlier planned dates are for Neil Simpson 5 and Osage 1 to 3, which reported March 2014 in the 2011 to 2013 editions and retired that month. Naughton 3 burned coal until its conversion to natural gas and is included for that reason. A missing date records what the owner reported to EIA; the form does not say why a date was added or removed. Every date shown for 2023, 2024 and 2025 was checked against EIA's own workbook.

Indefinitely postponed or cancelled

These remain in some datasets with a "proposed" status, which can overstate the capacity in development if they are not excluded.

PlantGeneratorTechnologyCapacity (MW)CountyStatusEIA plant ID
Chokecherry and Sierra Madre WindI-COnshore Wind Turbine500.0CarbonIP58987
Elk Basin Gasoline PlantEMGENNatural Gas Internal Combustion Engine0.7ParkIP52127
Medicine Bow12Onshore Wind Turbine0.7CarbonCN692
Medicine Bow13Onshore Wind Turbine0.7CarbonCN692
Uinta WindWIND1Onshore Wind Turbine119.0UintaIP68005

Interconnection queue

Before a generator can connect to the grid, its developer must request interconnection from the transmission provider and pass through a series of studies. Berkeley Lab's Queued Up data file gathers these requests from every queue in the country. It lists 400 requests for projects in Wyoming, covering requests through the end of 2025.

StatusRequestsCapacity (MW)
Withdrawn26962,148.1
Active7316,175.3
Operational515,134.0
Suspended72,359.0

At the end of 2025, 73 requests for 16,175.3 MW were active: 1.3 times Wyoming's existing capacity of 12,735.6 MW, and 2.2 times the 7,206.6 MW of proposed generators reported to EIA. A queue request is an early step, not a plan to build: 26 of the active requests (5,210.5 MW) had signed an interconnection agreement. Of the 247 Wyoming requests entered in 2020 or earlier, 48 (19%) reached commercial operation and 192 (78%) were withdrawn.

Active requests by technology

Technology (first resource)Active requestsCapacity (MW)
Wind325,692.7
Solar235,490.9
Gas113,062.7
Nuclear21,000.0
Battery5929.0

Active requests by study phase

Study phaseActive requestsCapacity (MW)
IA Executed265,210.5
In Progress (unknown study)223,720.1
Cluster Study143,257.0
Facility Study2550.0
System Impact Study1350.0

When requests are withdrawn

Of the 269 withdrawn requests, only 36 (13%) carry a withdrawal date, almost all of them from PacifiCorp. For those 36, the median time from request to withdrawal was 5.5 years, but so few are dated that the figure cannot be taken to represent Wyoming's queue as a whole.

Queue operatorWithdrawn requestsWith a withdrawal date
PacifiCorp24631
CLPT130
SPP32
PRPA20
PSCo22
CAISO11
MISO10
WAPA-IS10

Notes: figures count interconnection requests, not projects; one project can file more than one request, or file in more than one queue. Capacity is the first resource's size, so the storage part of a hybrid project is not added. The active capacity computed here for gas, solar and wind matches the Wyoming totals that Berkeley Lab publishes in the same file. Download: all 400 requests.

Reading this tracker

Download the data: proposed generators, planned retirements.